The title of the project

Construction and expansion of public transport infrastructure along with the purchase of a bus fleet in Grudziądz

Name of the beneficiary
COMMUNE OF THE CITY OF GRUDZIĄDZ
Project value
39 146 856,98 zł
Co-financing from the EU
29 361 604,15 zł
Voivodeship
kujawsko-pomorskie
County
m. Grudziądz
program
Regionalny Program Operacyjny Województwa Kujawsko-Pomorskiego na lata 2014-2020
action
3.4. Zrównoważona mobilność miejska i promowanie strategii niskoemisyjnych
fund
Europejski Fundusz Rozwoju Regionalnego
perspective
2014 - 2020

The project aim was to develop public transport infrastructure and to purchase new vehicles. The project understands the infrastructure development as the construction of new public transport roads and lines as well as the reconstruction of existing public transport roads and lines. The project was beneficial not only to the city of Grudziądz, but also to its inhabitants and visiting tourists.

In addition, the project implementation enabled the reduction of exhaust gases and toxic substances emission into the environment. Until the project conclusion, it was a significant city issue, therefore, it became one of the reasons for the project implementation.

Project in numbers:

  • Number of purchased units of passenger rolling stock in public municipal transport – 7 pcs.
  • The capacity of the purchased passenger rolling stock in public municipal transport – 616 pcs.
  • The total length of new or reconstructed public transport lines – 1,872 km
  • Length of constructed bicycle paths – 0.106 km
  • Length of supported bicycle infrastructure – 0.106 km

It is estimated that the project will increase the number of people using public transport and reduce the amount of greenhouse gases emission. The planned results of the project implementation are:

  • Number of public transport services on reconstructed and new public transport lines 15,741,980 items / year
  • Estimated annual decrease in greenhouse gas emissions of 76.69 tons CO2 equivalent per year

The project implementation was divided into several stages, and the schedule provided for their implementation in the following periods presents as follows:

  1. Documentation design: 07.2016 – 10.2017
  2. Feasibility study: 08.2017 – 10.2017
  3. Application for project co-financing: 08.2017 – 10.2017.
  4. Bus fleet purchase – 10.2018.
  5. Two fast charging stations purchase – 10.2018.
  6. Slow-charging devices purchase – 10.2018.
  7. Construction works: 04.2018 – 08.2020
  8. Investor’s supervision: 04.2018 – 09.2020

9. Promotional activities: 06.2018 – 09.2020

Your project description

To add a photo, description, specify a location or attach other materials about the project, you should fill out the form below. After clicking the “send” button, a message will be sent to you e-mail asking for confirmation. You must accept to submit the form. The EU Dot Map Guidelines and consent to the processing of personal data. materials will be sent to the editor of the site, who will publish it on the website after verification test.

Add photos project photos
Add a movie or presentation project films
Description of the project
Opis projektu

I declare that I have read the Regulations of the Online Website of the EU Mapa Dotacji and accept its provisions.

I agree to the processing of my personal data, entered in the contact form, in order to reply to the message. According to art. 13 para. 1 and 2 of the Regulation of the European Parliament and of the Council (EU) 2016/679 of 27 April 2016 on the protection of individuals with regard to the processing of personal data and on the free movement of such data and repealing Directive 95/46 / EC (Journal of Laws EU L 119, 04/05/2016, page 1) (RODO), I inform that:
1.administrator of personal data processed in the Ministry of Development Funds and Regional Policy, based at: ul. Wspólna 2/4 00-926 Warsaw, is the Minister of Development Funds and Regional Policy;
2. personal data will be processed in order to reply to a message, based on the provisions of art. 6 par. 1 lit. a) RODO;
3. personal data may be made available to other authorities entitled under the relevant provisions to obtain data;
4. in connection with the processing of personal data have the right to: – request access to their personal data, rectify or limit processing, – raise objections to the processing of personal data, – withdraw consent to processing at any time, – submit a complaint to the supervisory body – the President of the Office Personal Data Protection;
5. personal data is not subject to automated processing in order to make decisions, including profiling;
6. contact details to the Data Protection Officer in the Ministry of Development Funds and Regional Policy: Data Protection Supervisor, Ministry of Development Funds and Regional Policy, address: ul. Wspólna 2/4 00-926 Warsaw, e-mail address: IOD@miir.gov.pl